Warren Street

warrenfeature

We started the Warren Street project for the City of Dayton in December 2015. We are doing a complete street reconstruction with new walks, curbs, pavement and street lights. The project runs from US 35 south just past Miami Valley Hospital to Wyoming Street. We have completed the water main portion of the project through the winter and are currently getting ready to start cutting half of the old street and doing the prep work to start installing curbs and pavement. This job has been very challenging due the amount of unknown obstructions underground. We are scheduled to complete this project in the fall of 2016.