Union Village

Union Village- Milcon was awarded the Union Village project in the spring of 2018. This project entails doing the mass excavation and embankment, installing new streets including curbs, asphalt and walks, installing the sanitary sewer approx. 13,500 LF, storm sewer approx. 11,000 LF and water main approx. 7,800 LF to service a 36 acre development on the corner of State Routes 63 & 741. This project has been challenging due to wet summer we have had to date, unexpected limestone that has had to be removed, and unstable soil. Work was started in July of 2018 and should be completed early fall in 2019.