Warren County/Springboro 73 & 741

Warren-County_Feature

Milcon was awarded this project in the summer of 2017. This project consisted of reconstructing all four sides of the state route 73 and state route 741 intersection. This included new traffic signal, lighting, storm sewer and water main work. Due to the amount of traffic the new utilities all had to cross the road at night when the road was allowed to be closed. There was a large amount of contaminated soil and water found from businesses that were located at this intersection previously that had to be removed and taken off site for treatment.  This job will be substantially complete in December with the surface asphalt and seeding being finished in the spring of 2018.