Warren County/Springboro 73 & 741

Milcon was awarded this project in the summer of 2017. This project consisted of reconstructing all four sides of the state route 73 and state route 741 intersection. This included new traffic signal, lighting, storm sewer and water main work. Due to the amount of traffic the new utilities all had … [Read more...]

Piqua Shawnee Storm Sewer Improvements

Milcon was awarded this project in the fall of 2017 by the City of Piqua. The project consisted of installing a 7’x2’box culvert from the river in Piqua to the MCD levee, setting a flap valve manhole assembly structure then running 48”concrete storm sewer through the levee. A manual gate valve … [Read more...]

Brandt-Phoneton Waterline

Milcon was awarded this project by Miami County in the fall of 2016. The project was completed in the spring of 2017. This project installed a new water main and water services to the residents of the Brandt and Phoneton areas in Miami County. The ditches were regraded along the entire length of the … [Read more...]

Dayton International Airport Economy Parking Lot

This project consisted of reconstruction of the entire 22 acre Economy Lot including new lighting system, security camera system, new storm sewer, curbs, walks and lanscape. There were lighting and pavement upgrades in 6 other lots at the airport. The project was challenging in many ways 1- … [Read more...]

Planet Fitness in Fairfield

Milcon Commercial Concrete was awarded the contract for the Planet Fitness project in Fairfield, Ohio. Milcon excavated and placed footers, poured concrete walls and prepped and poured the 20,000 SF slab on grade and prepped and poured the 10,000 SF slab on deck. The picture shows one of the three … [Read more...]

FedEx Ground South Dayton Facility

FedEx Ground South Dayton Facility is a job that Milcon Commercial Concrete is currently working on. It is a 32-acre complex with 250,000sf under the roof. There were over 2,400lf of footer + 84 column pads on the main building. 1/3 of the footers had to be” hammered out” through rock. Inside the … [Read more...]

Oxford State Road

Milcon Concrete started the Oxford State Road project, located in the City of Middletown, May 24th, 2016. This job is a 11,200’ long complete road construction that includes new storm sewer, water main and services, new curb and paving, and new signals. There is 10,294’ of storm ranging in size from … [Read more...]

Otterbein

Milcon Commercial Concrete worked on Otterbein, a senior assisted living center in Lebanon Ohio. This project consisted of 1000’ of footer, 1000’ of basement wall and 67 column pads, all in a 13,000 SF basement footprint. Milcon Commercial Concrete began footers for the new building on May 16th, … [Read more...]

Upper Valley Medical Center

Upper Valley Medical Center (UVMC) is a project that Milcon Commercial Concrete worked on in Troy. This job consisted of a 20,500 SF new emergency department addition with a 2,500 SF lightweight deck and a 1,100 SF MRI addition. Footers started in March 2016 and slabs were finished in July 2016. … [Read more...]

PSA Hangar Addition

This is a project that our road construction division and our concrete division worked on together. Milcon started work on the PSA Hangar Addition Early Site Work Package in August and will finish in December. This project included building an 80,000 SF building pad, 11,000 CY of compacted fill, … [Read more...]